Period: 07.2017

Location: Považská Bystrica, Slovakia

Investor: Dongil Rubber Belt Slovakia, s.r.o.

In July 2017 was modified the floor in DRB Slovakia. Total work was done during one week of summer shutdowns only. The scope of work was removing the existing floor, creating reinforcement for extending the passages, demolition work, concrete floor casting including final polishing and final cleaning.

Považská Bystrica 20...